EU Machinery Regulation 2027: what machine builders and integrators must do now
On 20 January 2027 the EU Machinery Regulation (EU) 2023/1230 replaces Machinery Directive 2006/42/EC. There is no transition period and no parallel application: from that date new law applies to everything newly placed on the market. Anyone building, converting or linking machines should now check what that means for ongoing projects.
Author: Alois Gruber, Managing Director · EngineeringPublished: Reading time: 8 min
In short
Regulation (EU) 2023/1230 applies bindingly from 20 January 2027 and replaces Machinery Directive 2006/42/EC without a transition period. New elements include explicit cybersecurity requirements for machinery, rules for machines with self-evolving behaviour, a changed list of high-risk machinery and the option to provide instructions digitally. Anyone making a substantial modification to a machine counts as the manufacturer themselves.
Until 19 Jan 2027
Machinery Directive 2006/42/EC
Anything placed on the market by then follows the old directive.
20 Jan 2027
Machinery Regulation (EU) 2023/1230
Applies to everything newly placed on the market from that day. No transition period, no parallel application.
After that
Substantial modification
A retrofit to existing machinery can also count as placing it on the market anew.
01The deadline and why it is hard
Regulation (EU) 2023/1230 was published on 29 June 2023 and applies from 20 January 2027. Unlike earlier transitions there is no grace period in which old and new rules could be applied side by side. For a machine placed on the market for the first time after that date, the new law applies in full.
In practice that means long-running projects starting in 2026 and delivered in 2027 must be designed to it now. Conformity assessment, technical documentation and instructions then already follow the Regulation. Converting afterwards is considerably more laborious than planning correctly from the start.
02What changes in substance
The basic system remains: risk assessment, essential health and safety requirements, conformity assessment, technical file, CE marking. What is new is above all what has grown onto machines over the past twenty years.
- Cybersecurity: the Regulation explicitly requires protection of controls against manipulation. Safety functions must not be defeatable by an attack.
- Machines with self-evolving behaviour: systems that change their behaviour in operation, for instance through learning methods, face additional requirements for risk assessment and evidence.
- Revised list of high-risk machinery: the former Annex IV list has been reworked; for certain machines involving a notified body becomes necessary or ceases to apply.
- Digital instructions: instructions may be provided digitally. On the user's request a paper version must be supplied free of charge within one month; safety-related information must still be delivered on paper.
- Software as a standalone safety component: software with a safety function is treated as a product rather than only as part of the machine.
03When a change becomes a substantial modification
The point that matters most to integrators and operators concerns conversions. A change counts as substantial when it creates a new hazard or increases an existing risk so much that the existing protective measures no longer suffice. Whoever makes such a change legally becomes the manufacturer of the modified machine. With all obligations from risk assessment to CE marking.
Not every change reaches that threshold. Replacing a defective component with an equivalent part is not a substantial modification. Pure data acquisition without intervening in the process also normally stays uncritical. But as soon as speeds increase, guards are rebuilt or handling is automated, the assessment must come before implementation.
04What this means for a retrofit
Retrofits on existing machinery are core business for many integrators, and it is exactly here that the assessment decides effort and responsibility. We therefore settle before quoting whether a substantial modification exists, and state explicitly in the quotation who declares conformity for which scope.
For operators this is not a bureaucratic detail but a liability question: anyone converting a machine, or having it converted, without that assessment stands without evidence if something goes wrong.
05Cybersecurity as a machinery topic
Explicitly including cybersecurity is the change with the greatest practical reach. A controller whose safety function can be influenced through an open remote maintenance connection does not meet the requirement. That brings together what many companies organise separately: machine building and network security.
In concrete terms it concerns network segmentation between production and office, controlled rather than permanently open remote access, and the question of who may change controller software. From 2027 these points belong in the machine's technical documentation.
06What to do now
Three steps make sense regardless of company size and can be done without great effort.
- Sort current and planned projects by whether delivery falls before or after 20 January 2027. Everything after that is designed to the Regulation.
- For every planned change to existing machinery, assess in advance whether a substantial modification exists, in writing, not in conversation.
- Review access to machine controls: who can change what, and from where? From 2027 permanently open maintenance connections are not merely a security risk but a conformity problem.
This article provides information on the legal situation and does not replace legal advice. For a binding assessment of your company please consult your legal advisers.
Frequently asked questions
Frequently asked questions
Do I have to convert my existing machinery by 2027?
No. The Regulation applies to machines placed on the market for the first time from 20 January 2027. Existing machinery may continue to be operated. Conversions do have to be checked: if a substantial modification is made, manufacturer obligations apply anew.
Who produces the risk assessment and the instructions?
The manufacturer of the machine. In the case of a substantial modification that is whoever makes the change. When we convert a machine, the quotation states explicitly who bears that responsibility and which documents are produced.
May the instructions be delivered digitally?
Yes. The Regulation allows digital provision. On request a paper version must be supplied free of charge within one month, and safety-related information must still be included on paper.
What does the Regulation newly require on cybersecurity?
Controls must be designed so that safety functions cannot be defeated by manipulation. That concerns remote access, software changes and the machine's network connection. Points that were previously mostly regulated outside the machine documentation.
Does the Regulation also apply to linked lines?
Yes. Anyone linking several machines into an assembly becomes the manufacturer of that assembly and must carry out their own conformity assessment.
Related services
Related
Cabinet manufacturing
We build switchgear assemblies for machine and plant builders: single enclosures, cabinet rows, control desks, command boxes and terminal boxes. Either as pure contract manufacturing to your diagram, or as a complete solution in which electrical design, manufacturing, testing and documentation come from one source.
Collaborative robot systems
A collaborative robot works alongside people because force and pressure on contact are limited. That makes it interesting for workplaces with no room for a fence and for tasks that change frequently. It is never the robot that is collaborative, always the application. And that is precisely the part that takes work.